A Supplier Capacity Questionnaire for Critical Parts

“A capacity figure without its shift pattern, losses and records is a promise, not evidence; the questionnaire's job is to make every bidder's promise checkable before award.”
| Statistic | Source |
|---|---|
| An automotive run-at-rate guide defines APW as average planned weekly volume and MPW as the maximum the customer may call. | Blažek, QM Bench, 2026 |
| Concentric requires a supplier's process to be able to produce 120% of the quoted volume with production tools and equipment, in the quoted work patterns. | Concentric supplier manual, 2025 |
| Theoretical capacity is set by the number of shifts, the capacity available per shift and the number of machines and workers. | Schönsleben, ETH Zurich, 2024 |
| In Nemak's planning rule, a projected 2% scrap rate at one operation raises the capacity needed at the operation before it from 100 to 102 a day. | Nemak supplier manual, 2021 |
| A 2019 medical device supply agreement set normal capacity at 5 days a week on 2 or 3 shifts per plant, with surge capacity stated separately. | Medtronic and IntriCon agreement, 2019 |
Each row restates one source's own scope. None is a capacity, utilization, scrap or surge benchmark for other buyers or parts.
What is a supplier capacity questionnaire for critical parts?
In this guide, a supplier capacity questionnaire is the part of a sourcing event that asks each bidder how it would make the buyer's volume of one critical part: machines, shifts, cycle times, tools and losses. In this guide's view, it makes answers comparable and checkable; on-site verification and post-award escalation are separate steps that follow.
Which machine, shift and tooling facts should the questionnaire ask for?
Ask for the inputs, not only the result. In Schönsleben's ETH Zurich course on capacity management, theoretical capacity is determined by the number of shifts, the capacity available in each shift and the number of machines and workers, and rated capacity multiplies it by planned capacity utilization and work center efficiency. Collecting each input separately shows which assumption carries a bidder's figure.
Ask per operation rather than per plant. Under the capacity planning rule in Nemak's supplier quality manual, suppliers base capacity plans on surrogate OEE data from similar products or equipment in their facility, or on machine maker data for a new process, and account for load and unload time. The rule also asks for each operation's projected scrap rate, because scrap raises the capacity needed upstream.
State the operating pattern as days, shifts and net hours, and ask which pattern the price assumes. In a 2019 supply agreement between Medtronic and IntriCon, filed with the SEC, normal capacity meant manufacturing to forecast 5 days a week on 2 shifts at two plants and on 3 shifts at a third. In this guide's view, a baseline that already needs weekend work leaves less room for surge.
In a production scheduling vendor's guide to tooling bottlenecks, dedicated tooling belongs to one part number, shared tooling such as a fixture set serves several part families, perishable tooling such as cutting tools is limited by availability and lead time, and waiting for a shared tool does not appear in machine utilization reports. In this guide's view, ask for each tool's sharing, sets, owner, life and replacement lead time.
How do demonstrated, quoted maximum and surge capacity differ?
In this guide, demonstrated capacity is good output a supplier's records show on the stated pattern; quoted maximum is what the supplier says the process could make; surge capacity is extra volume a buyer contracts for at set notice and duration. In an automotive run-at-rate guide by a process quality lead, APW is the average planned weekly volume and MPW the maximum the customer may call.
In the ETH Zurich capacity management course, desired capacity utilization should generally be less than 100% to avoid long queue times, and load should be scheduled to rated capacity, not theoretical capacity. In this guide's view, ask bidders for the utilization behind any quoted maximum, and treat near-full loading as a ceiling, not a plan.
In Concentric's global supplier manual, the supplier's process must be able to produce 120% of the quoted volume with production tools and equipment, in the quoted work patterns, fixtures and tooling. In this guide's view, that makes the stated pattern and tooling part of the quote, so record them for any later check.
In the Medtronic and IntriCon agreement, surge capacity was an amount above regular capacity covering materials, resources and equipment in the same timeframe as the normal forecast, and the supplier was responsible for identifying the capital equipment needed to expand capacity. The public filing redacts the surge amount.
In this guide's view, ask how surge would be produced: added shifts, more machines or tool sets, a faster rate or a named subcontractor. A faster rate, or moving work to a subcontractor or another site, changes the approved process, so require the buyer's approval before either is used. Each route needs its own evidence, so ask for its notice period, maximum duration, people, equipment and price.
What evidence should each answer carry?
In this guide's view, every figure should name its source record and say whether it is measured or estimated; the table below lists a record for each field. In Nemak's supplier quality manual, required capacities reflect acceptable shippable product within a specified operating pattern, and planned ideal cycle times are the supplier's best estimate from similar processes or machine makers' quotes.
How should answers be normalized and scored across bidders?
Convert every answer to good parts per week on the buyer's operating pattern before comparing. In the automotive run-at-rate guide on QM Bench, the common mistakes include counting all parts instead of good parts, assuming the line runs 24 hours a day, every day, instead of its real working pattern, and forgetting that a shared machine gives only part of its time to the part.
According to an ISO 22400-2 reference page from MachineWise, two plants that define planned production time differently, one excluding planned maintenance and breaks and the other including them, can report OEE figures many points apart while both are internally correct. In a peer-reviewed case study of one plastics production line in Jordan, three months of 2020 data from six machines put speed losses at 58.1% and planned and unscheduled disruptions at 12.73% of all losses. In this guide's view, require the time base and all three OEE factors with every figure, and recompute on one basis.
In this guide's view, score each bidder at its bottleneck: count each operation's weekly output in finished good parts, after scrap at that operation and at every later one and after shared-machine allocation, and take the lowest. Record its margin over average and peak weekly demand. Rate the evidence separately, so a documented modest margin is not outscored by an unsupported large one.
Which answers should trigger verification?
In an OEE software vendor's article on how OEE gets manipulated, the tactics include excluding scheduled maintenance from the available time and labeling unplanned stoppages as scheduled downtime, and a performance score of 110% or more is called a sign of an artificially lowered speed baseline. In this guide's view, send an answer to verification when:
- It has no record, or the record is not comparable: a different process, equipment, material or operating pattern.
- Demonstrated output at the bottleneck is close to or below peak demand.
- An OEE figure has no time base, or performance is above 100%.
- Surge depends on hiring, new equipment, a faster rate or an unnamed subcontractor.
- Two answers contradict each other, such as a cycle time that cannot yield the stated output.
Site visits, a run at the quoted rate and capability evidence are separate, later steps. Set how deep they go by the part's criticality, using the tiers of a structured supplier risk assessment.
What should a critical-part capacity questionnaire contain?
The questionnaire below turns these decisions into fields a category team can issue with a request for quotation. It is an authored planning aid, not a standard.
| Question | Answer on this basis | Evidence to attach | Send to verification when |
|---|---|---|---|
| Buyer's basis (issued with the form) | Average and peak weekly demand, operating pattern, unit and OEE time base | None; the buyer sets it | Answered on another basis |
| Process route | Operations in order, in-house or subcontracted | Process flow | An operation or subcontractor is unnamed |
| Machines | Number per operation, dedicated or shared, the part's hours on shared machines | Machine list with maintenance windows | Shared-machine hours are missing |
| Cycle time | Ideal cycle time per operation, with load and unload | Comparable-part records or a machine maker's quote | Estimated only, or faster than records |
| Operating pattern and labor | Days, shifts, net hours and headcount by role per shift | Shift pattern with current overtime | Baseline already needs overtime |
| Losses | Availability, performance, quality and scrap per operation, with the time base | OEE and scrap records for a comparable part | No time base, or performance above 100% |
| Tooling | Dedicated or shared, sets, owner, life and replacement lead time | Tooling list | One tool set with a long lead time |
| Demonstrated capacity | Good parts per week at the bottleneck on the stated pattern | Output and downtime logs | Near or below peak demand |
| Quoted maximum | Highest weekly output and the utilization it assumes | Capacity calculation per operation | Near-full loading or round-the-clock running |
| Surge offer | Extra weekly volume, notice, duration, route and price | Surge plan naming roles, equipment and subcontractors | Relies on hiring, new equipment, a faster rate or an unnamed subcontractor |
| Constrained inputs | Materials, special processes or sub-suppliers that limit output | Sub-supplier confirmations | A single source, or no confirmation |
| Committed load | Hours already committed on the bottleneck, in aggregate | Aggregate loading statement | Leaves less than peak demand |
Illustrative fields only; margins, thresholds and scoring weights are for each buyer to set with engineering and quality. None is a benchmark.
Issue the form with the quotation stage of a structured sourcing workflow, so every bidder answers the same rows in the same units. Issue it under the request's confidentiality terms, let bidders redact other customers' data from shared-machine records, and say whether the answers will be written into the contract. Guides on verifying supplier capability and escalating capacity risk after award are listed in the Journal's guide library.
How do AI agents change supplier capacity questionnaires?
Frequently asked questions
What is the difference between rated and demonstrated capacity?
In the ETH Zurich capacity management course, rated capacity is theoretical capacity times planned capacity utilization times work center efficiency. In this guide, demonstrated capacity is the good output a supplier's records show on the stated pattern. Question a rated figure well above the demonstrated one.
Should surge capacity count in a bidder's capacity figure?
Not by itself. In the Medtronic and IntriCon supply agreement, surge capacity was a separate amount above regular capacity covering materials, resources and equipment. Ask for its volume, notice, duration, route and price, and judge it apart from baseline capacity.
Can bidders' OEE figures be compared directly?
Only on the same time base. According to MachineWise's reference page on ISO 22400-2, a vendor's summary of the standard, plants that define planned production time differently can report OEE figures many points apart. Ask for availability, performance and quality with the definition of planned production time, and recompute on one basis.
Sources
- Run at rate: how to verify capacity for PPAP, step by step — Ľubomír Blažek, QM Bench (qmbench.com); updated 6 November 2026, 2026. Contextual evidence (practitioner article): Definitions of APW (average planned weekly volume) and MPW (the maximum the customer may call); common mistakes when stating capacity: counting all parts instead of good parts, using a 24-hour week instead of the real working pattern, and forgetting that a shared machine gives only part of its time to the part.
- ISO 22400-2 OEE Definitions Reference — MachineWise, MachineWise (machinewise.in, machine monitoring software vendor); reference page dated 28 September 2026, 2026. Contextual evidence (practitioner article): ISO 22400-2 element definitions (availability, effectiveness, quality); two plants with different definitions of planned production time can report OEE figures many points apart while both are internally correct; establish the time base before comparing.
- Global Supplier Manual 2025 (Supplier Specific Requirements Manual), Issue 2 — Concentric AB, Concentric AB; Issue 2, January 2025, 2025. Contextual evidence (practitioner article): The supplier's process must be able to produce 120% of the quoted volume with production tools and equipment, in the quoted work patterns, fixtures and tooling, which ties the capacity check to the basis the supplier quoted.
- 14.1.1 Capacity, Work Center Efficiency, and Rated Capacity — Paul Schönsleben, ETH Zurich (opess.ethz.ch), online course on Integral Logistics Management, section 14.1; page published 19 November 2024, 2024. Foundational evidence (industry analysis): Theoretical capacity is determined by the number of shifts, the capacity available per shift and the number of machines and workers, with no adjustment for unplanned downtime; rated capacity is theoretical capacity times planned capacity utilization times work center efficiency; desired utilization should generally be below 100% to avoid long queue times; load should be scheduled to rated rather than theoretical capacity.
- Supplier Quality Manual — Nemak, Nemak; revision date 21 December 2021 (initial date 7 December 2017), 2021. Contextual evidence (practitioner article): Capacity plans must use surrogate OEE data from similar product lines or equipment in the supplier's facility, or machine maker data for a new process; planned ideal cycle times are the supplier's best estimate from similar processes or machine makers' quotes; load and unload time must be accounted for; projected scrap per operation raises the capacity required upstream (100 a day becomes 102 a day at 2% scrap); required capacities reflect acceptable shippable product within a specified operating pattern; similar planning is expected of sub-suppliers.
- Master Supply Agreement between Medtronic, Inc. and IntriCon Corporation (Exhibit 10.1) — Medtronic, Inc.; IntriCon Corporation, US Securities and Exchange Commission, EDGAR; filed by IntriCon Corporation as Exhibit 10.1 to its Form 10-Q for the quarter ended 30 September 2019 (filed 8 November 2019), 2019. Historical evidence (official report): Normal capacity defined as manufacturing to forecast 5 days a week on 2 shifts at two plants and 3 shifts at a third; surge capacity stated separately as an amount above regular capacity covering materials, resources and equipment in the same timeframe as the normal forecast; supplier responsible for identifying capital equipment to expand capacity; the surge amount is redacted.
- When Tooling Is Your Bottleneck: Scheduling Tools, Fixtures, and Dies Like Machines — User Solutions Team, User Solutions (production scheduling software vendor); published 27 April 2026, 2026. Contextual evidence (practitioner article): Dedicated tooling belongs to one part number; shared tooling such as fixture sets and inspection programs serves several part families; perishable tooling is limited by availability and lead time; waiting for a shared tool does not appear in machine utilization reports.
- 3 Ways OEE Gets Manipulated and How to Spot Them — Evocon, Evocon (OEE monitoring software vendor); published 29 May 2025, modified 13 October 2025, 2025. Contextual evidence (practitioner article): The time base is the easiest place to manipulate OEE; tactics include excluding scheduled maintenance from the available time and labeling unplanned stoppages as scheduled downtime; performance scores of 110% or more indicate an artificially lowered speed baseline.
- Evaluation and Improvement of a Plastic Production System Using Integrated OEE Methodology: A Case Study — Sahar ALMashaqbeh; Eduardo Munive Hernandez, Management Systems in Production Engineering 32(3):450-463, 2024 (STE Group / Sciendo; DOI 10.2478/mspe-2024-0042); copy with cover sheet in the University of Bradford repository (hdl 10454/20120), 2024. Current empirical evidence (peer reviewed journal): Three months of data under real working conditions on one line; speed losses 58.1% and planned and unscheduled disruptions 12.73% of all losses; availability measured as operating time over loading time. Supports asking bidders for OEE as availability, performance and quality with its time base rather than one figure.