VP of supply chain at the owner
Owns the long-lead orders and the slot reservations.
A verified lead time on every long-lead line, with alternatives already screened against the specification.
Before you go
One sharp email on procurement markets — what moved, why it matters, what to do about it. Daily or weekly. Unsubscribe anytime.

Zinit Industries Power plants
With gas turbines booked for years and a step-up transformer taking nearly three to arrive, the equipment list now decides the commercial operation date. Zinit's AI agents check every long-lead line against the date the plant needs it, find a qualified supplier who can deliver sooner, and run the bidding so the earlier slot wins.
the average wait for a generator step-up transformer in mid-2025, against about 50 weeks for a transformer in 2021 (Wood Mackenzie).
what one US utility agreed to pay its turbine maker to reserve a manufacturing slot for a plant entering service in 2030, a step its filing says did not exist two years earlier.
US utilities forecast over the next five years, up from 24 GW in the forecast three years earlier (Grid Strategies).
What PJM pays for capacity, $ per MW-day, by delivery year
Worked example: a month late on the 620 MW plant above, in PJM
$10.7M a month
Our arithmetic from the cited prices, before lost energy margin and any delay damages in the offtake contract, which your own contracts set. If the plant cleared PJM's auction and misses its delivery year, PJM also charges the clearing price plus 20% for each day of the shortfall. In ERCOT, with no capacity payment, the month is lost energy margin and interest.
A new plant is bought by a committee and built by a chain of parties, and each of them owns a piece of the date.
Owns the long-lead orders and the slot reservations.
A verified lead time on every long-lead line, with alternatives already screened against the specification.
Owns the construction schedule and the owner-furnished equipment.
Delivery dates set against the milestones that need them: switchyard energization, backfeed and first fire.
Owns the deposits, the delay damages and the financing.
The cost of a slip per line, formula in view, forfeited deposits included.
Owns the specification and every supplier on it.
Candidates screened against the spec before anyone calls them; the veto stays theirs.
Owns the factory slots.
A competitive event scored on delivery date, so the earlier slot wins.
Owns the interconnection and the switchyard equipment it will accept.
A search limited to its standards and accepted makers from the start.
What Zinit doesEvery long-lead line checked against switchyard energization, backfeed and COD on day one.
What Zinit does103M+ suppliers searched, narrowed to the makers your spec and the transmission owner accept; the factory's own quote confirms the slot.
What Zinit doesBids scored on delivery date as well as price.
What Zinit doesCandidates screened first, so their reviews run while the bids are in.
What Zinit doesCost of delay per line, formula in view, deposits included.
103M+ suppliers, AI agents that find and screen them and run the bidding, and procurement people who work beside your team.
Each long-lead line's delivery date against the date the site needs it, from the switchyard to first fire.
The risk to the COD, in weeks and money.
A factory that meets the specification and ships earlier, confirmed by its own quote, because no maker's queue sits in a database.
A vetted alternative with a quoted slot.
The event is set up from your equipment list and your engineer's datasheets in under an hour, the bids take the weeks they take, and your team awards.
Weeks back on the schedule.
Sometimes no factory beats the incumbent's date, and then you know it in weeks rather than at the factory test. The turbine slot you already hold stays yours, since this work sits around it: on the transformers, the breakers and the balance of plant.

Click a step. Zinit is connected to your project drive, schedule and ERP, so nothing is uploaded. Every figure belongs to the example plant.
Connected sources, already read
Equipment read from the specification, linked to the schedule
| Line | Qty | Spec | Named supplier | Activity | |
|---|---|---|---|---|---|
| Gas turbine | 2 | F-class, 60 Hz | Incumbent OEM, slot held | Power island | p. 18 |
| Step-up transformer | 3 | 250 MVA, 345/18 kV | Incumbent OEM | Switchyard backfeed | p. 64 |
| HV circuit breaker | 6 | 362 kV, 63 kA, dead tank | Incumbent OEM | 345 kV switchyard | p. 71 |
| HRSG | 2 | Triple pressure, reheat | Incumbent OEM | Power island | p. 33 |
| Cooling tower | 1 | 10-cell, counterflow | Incumbent OEM | Circulating water | p. 102 |
Lead times against the date needed on site
| Line | On site | Needed | Lead time | Ordered | Source |
|---|---|---|---|---|---|
| Step-up transformer | Week 156 | Week 130 | 152 weeks | Week 4 | Quote, 3 Sep |
| HV circuit breaker | Week 146 | Week 130 | 142 weeks | Week 4 | Quote, 28 Aug |
| Gas turbine | Week 98 | Week 104 | Slot held | Reserved | Reservation |
| HRSG | Week 92 | Week 100 | 84 weeks | Week 8 | Quote, 1 Sep |
| Cooling tower | Week 72 | Week 110 | 60 weeks | Week 12 | Quote, 20 Aug |
Forecast COD: week 182. The step-up transformers set the date, and the breakers are 16 weeks late behind them, which the schedule's critical path does not show.
Delay against the planned COD
| Per month: $10.7M | Basis | |
|---|---|---|
| Capacity payments not earned | 620 MW × 74% accredited × $329.17 × 30.4 days = $4.6M | in the $10.7M |
| Interest during construction | 7% a year on the debt drawn by COD = $6.1M | in the $10.7M |
| Energy margin not earned | Expected output × spark spread | add yours |
| Offtake delay damages | From the PPA or tolling agreement | add yours |
| Cancellation charges and re-engineering | If a line moves supplier | add yours |
Two sourcing events recover 18 of the 26 weeks
On site in week 138 instead of 156, screened against the spec; the owner's engineer reviews while the bids are in.
Once the transformers move, breakers due in week 146 set the date, so the event asks for week 138 or sooner.
The plant still finishes 8 weeks late, about $20M of delay cost. Cancellation charges are an assumed 20% of each order, and your purchase order's termination schedule decides the real figure.
Supplier Search, prefilled from the specification
| Supplier | Region | Lead time | On site | Spec gaps | Source |
|---|---|---|---|---|---|
| Transformer OEM A | Europe | 130 weeks | Week 138 | None found | RFQ reply, 2 Sep |
| Transformer OEM B | North America | 141 weeks | Week 149 | None found | RFQ reply, 29 Aug |
| Transformer OEM C | East Asia | 118 weeks | Week 126 | Sound at ONAF rating | RFQ reply, 1 Sep |
Every lead time here is that factory's own reply to the RFQ, which asks for the factory-test week and the date on site, not only ex-works, because no maker's queue sits in a database. OEM C is faster and misses the sound limit, so it stays off the shortlist unless your engineer asks for it.
Zinit runs the same check on every plant, and the lines that decide the date change with the technology. Pick the plant you are building.
What sets the date
Where sourcing moves it
Around the turbine you already hold: the transformers, the breakers, the HRSG and the balance of plant, where a second qualified maker usually exists.
What sets the date
Where sourcing moves it
The units themselves, bid across the engine and aeroderivative makers; refurbished aeroderivatives have been offered for delivery in 2027.
What sets the date
Where sourcing moves it
A supplier search that checks the foreign-entity rule alongside the delivery date, so the earlier slot does not cost the credit.
What sets the date
Where sourcing moves it
Balance-of-plant and non-safety scopes, and replacements for obsolete equipment, bid like any other line; safety-related items stay inside your Appendix B program.
Figures from the cited sources. Dates and thresholds move, so your own quotes and counsel decide.
Lead time is the wait from order to delivery. Grey is the earlier benchmark and pink the latest published one, solid to the low end of the range.
The long-lead lines, the lever on each, and the manufacturers the search runs across.
Wait today3 to 6 years
The slot you hold is the asset; where the design and the air permit allow, aeroderivatives or a refurbished unit can bridge the gap sooner.
Wait today143 weeks average
A second qualified factory, bid on delivery date, with impedance, sound and cooling settled before the bid.

Wait today151 weeks (late 2023)
A date-weighted event across the makers the transmission owner accepts.
Wait todayWith the power island
Owners now buy HRSGs before the EPC is hired, so bid across the specialist makers as soon as the turbine model fixes the exhaust conditions.
Wait today18–36 months
Smaller units for peaking or bridge power, bid across the engine and aeroderivative makers.
Established manufacturers in each category, shown to illustrate the market. They are not customers, partners or users of Zinit.
Keep it, and nobody contacts your turbine maker about it. The turbine is rarely the line Zinit changes; the work is on the step-up transformers, breakers, HRSGs and balance of plant around it, where a second qualified maker usually exists.
Then the search starts from its standards and its list of accepted makers, which your team provides, before any supplier is invited.
They keep the veto, and nobody is invited until your team approves the list. Zinit's agents and people screen on specification, test standards, references and lead time, and your engineers qualify while the bids are in, not after the award.
Many owners now buy the longest lines themselves and hand them to the EPC as owner-furnished equipment. Zinit works for whoever places the order, the owner before notice to proceed or the EPC after it.
Nothing here cancels them. The second source is for the line whose slot already misses the date, and any deposit or cancellation charge sits inside the recovery calculation.
The bids are scored on the date on site. The RFQ asks each factory for the factory-test week and the delivered date, and your team sees both.
They do not need to. The example works from the equipment list, the datasheets and the schedule, and suppliers see only the RFQ package your team approves.
The same rules apply to any line with a need-by date: transformers and switchgear for a peaker or storage site, or parts and services for an outage window, get the same check and the same date-weighted bidding.
Zinit is supplier-funded and free to buyers, the same as the rest of the platform: the suppliers who compete for your business fund it.
It does not manufacture equipment, hold inventory or reserve factory slots, and it does not replace your schedule, your ERP or your engineers' judgement. Sometimes no factory beats the incumbent's date, and then you know it in weeks.
See which lines put your COD at risk before you commit to anything. Your team directs and approves, and Zinit's procurement people work alongside yours.
Sources