VP sourcing and supply chain
Owns the long-lead orders and the date.
A verified lead time on every long-lead line, and the alternatives already screened against the design.

Zinit Industries Data centers
Every month a data center runs late costs about 5% of the project. Zinit finds the long-lead lines that will be late, a supplier who can deliver sooner, and runs the bidding so the shortest delivery wins.
for every month a data center runs late.
the developer’s direct cost of a month’s delay on a 60 MW build (STL Partners).
the wait for a power transformer today; about 50 before 2020 (Wood Mackenzie).
A month of delay on a 60 MW build
$14.2M
Before debt carry. STL Partners: more than a 25% decline in IRR.
Bought by a committee, built by a chain of parties who each own a piece of the date.
Owns the long-lead orders and the date.
A verified lead time on every long-lead line, and the alternatives already screened against the design.
Owns the shell and the fit-out.
Delivery dates set against the milestones that need them.
Owns the deposits and the penalties.
The cost of a slip per line, formula in view, forfeited deposits included.
Owns the specification and every supplier on it.
Candidates screened against the spec before anyone calls them; the veto stays theirs.
Owns the factory slots.
A competitive event scored on delivery date, so the earlier slot wins.
Owns energization, and the list of manufacturers it accepts.
A search limited to that list from the start.
What Zinit doesEvery long-lead line checked against its need-by date on day one.
What Zinit does103M+ suppliers searched against the spec; the factory’s quote confirms the slot.
What Zinit doesBids scored on delivery date as well as price.
What Zinit doesCandidates screened first; the review runs while bids are in.
What Zinit doesCost of delay per line, formula in view, deposits included.
103M+ suppliers, AI agents that find and screen them and run the bidding, and procurement people beside your team.
Each long-lead line’s delivery date against the date the site needs it.
The risk to the date, in weeks and money.
A factory that meets the spec and ships earlier, confirmed by its own quote.
A vetted alternative with a quoted slot.
Set up in under an hour; bids scored on date and price; your team awards.
Weeks back on the schedule.
Click a step. Zinit is connected to your project drive, schedule and ERP; nothing is uploaded.
Connected sources, already read
Equipment read from the design, linked to the schedule
| Line | Qty | Spec | Named supplier | Activity | |
|---|---|---|---|---|---|
| Power transformer | 2 | 60 MVA, 132/33 kV | Incumbent OEM | Utility substation | p. 14 |
| MV switchgear | 6 | 33 kV, 2500 A | Incumbent OEM | Electrical rooms | p. 22 |
| Generator set | 8 | 3 MW, diesel | Incumbent OEM | Generator yard | p. 31 |
| UPS system | 12 | 1.6 MW, static | Incumbent OEM | Electrical rooms | p. 27 |
| Chiller | 6 | 2.5 MW, water-cooled | Incumbent OEM | Central plant | p. 40 |
Lead times against the date needed on site
| Line | Lead time | Source | Delivery | Needed |
|---|---|---|---|---|
| Power transformer | 128 weeks | Quote, 3 Sep | Week 130 | Week 106 |
| MV switchgear | 64 weeks | Quote, 28 Aug | Week 70 | Week 100 |
| Generator set | 80 weeks | OEM portal, 1 Sep | Week 88 | Week 102 |
| UPS system | 40 weeks | Quote, 3 Sep | Week 48 | Week 104 |
| Chiller | 44 weeks | Quote, 20 Aug | Week 54 | Week 100 |
Forecast completion: week 130. The transformer is on the critical path.
Delay against the original deadline
| Cost of delay, per month | Basis | |
|---|---|---|
| Lost lease revenue | 40 MW × $190/kW/month | assumption |
| Debt carry | Drawn loan × rate | assumption |
| Standby contractors | Extended general conditions | assumption |
| Contract penalties | From the tenant agreement | assumption |
| Deposits forfeited and re-engineering | If a line moves supplier | assumption |
Two ways to recover the date
110 weeks against 128, spec-screened; the engineer reviews while bids are in.
Switchgear, generators, chillers bid on date and price.
Supplier Search, prefilled from the design
| Supplier | Region | Lead time | Certificates | Spec match | Source |
|---|---|---|---|---|---|
| Transformer OEM A | Europe | 110 weeks | IEC 60076 | Full | RFQ reply, 2 Sep |
| Transformer OEM B | North America | 118 weeks | IEEE C57 | Full | RFQ reply, 29 Aug |
| Transformer OEM C | East Asia | 104 weeks | IEC 60076 | Partial | RFQ reply, 1 Sep |
Lead time is the wait from order to delivery. Grey: before 2020. Pink: today.
The critical-path lines, the lever on each, and the manufacturers the search runs across.
Wait today128–144 weeks
A second qualified OEM, or a unit built to a standard the design already accepts.

Wait today52–80 weeks
A date-weighted event across the platforms that meet the spec.
Wait today90–110 weeks
Bid across the major engine builders. 1.5–3 MW sets: 50–78 weeks.
Wait today30–60 weeks
Committed early; modular units from a second source close a gap.
Wait today48–60 weeks
The plant gates the fit-out; compete it across the large-chiller makers.
Established manufacturers in each category, shown to illustrate the market. They are not customers, partners or users of Zinit.
Keep them. Zinit reads what you have and hands the recovered dates back; an overlay for the long-lead lines, not a new system of record.
They do not have to. Lead times come from the quotes, FAT documents and portals you already receive; an alternative’s slot is confirmed by that factory’s own quote.
They keep the veto. Zinit screens on spec, certificates, region and lead time; your engineer qualifies while the bids are in, and a utility’s approved list limits the search from the start.
Nothing here cancels them. The second source is for the line whose slot already misses the date, and any forfeited deposit sits inside the recovery calculation.
Zinit is supplier-funded and free to buyers, the same as the rest of the platform: the suppliers who compete for your business fund it.
It does not manufacture, hold inventory or reserve slots, and it does not replace your schedule, your ERP or your engineer’s judgement. Sometimes no factory beats the incumbent’s date; then you know it in weeks.
See which lines put your date at risk before you commit to anything. Your team directs and approves; Zinit’s procurement people work alongside yours.
Sources