Enterprise Energy Procurement and Natural Gas Hedging

“I would put every site’s peak tags and every broker fee on one page before choosing between fixed and index supply, because a contract can only fix the costs someone has written down.”
| Statistic | Source |
|---|---|
| PJM, July 14, 2026: 2028/2029 capacity cleared RTO-wide at the $325.00 cap per megawatt of unforced capacity per day. | PJM auction report, 2026 |
| EIA, November 10, 2026: Henry Hub forecast at $2.87 per MMBtu for November to March, 16% below the prior month’s forecast. | EIA energy outlook, November 2026 |
| NIH, May 2026: peak forecasting and load reduction cut one plant’s peak load contribution by about 25%. | NIH technical bulletin, 2026 |
| Secomandi and Kekre, 2014: in their procurement model, buying the demand forecast forward was nearly optimal on natural gas instances. | Refereed study by Secomandi and Kekre, 2014 |
| Berkeley Lab, 2005: all 8 suppliers interviewed offered fixed, spot-indexed and block-and-index supply. | Berkeley Lab supplier interviews, 2005 |
Current figures first; dated figures, not any buyer’s costs.
- 2022/2023 delivery year$50.00
- 2023/2024 delivery year$34.13
- 2024/2025 delivery year$28.92
- 2025/2026 delivery year$269.92
- 2026/2027 delivery year$329.17
- 2027/2028 delivery year$333.44
- 2028/2029 delivery year$325.00
RTO resource clearing prices from Table 2 of PJM’s July 14, 2026 auction report, in dollars per megawatt of unforced capacity per day. The 2026/2027 to 2028/2029 auctions ran under a price cap and floor, 2028/2029 cleared at its $325.00 cap, and constrained zones can clear higher. Wholesale results, not any buyer’s capacity charge. Source: PJM Interconnection, July 14, 2026.
What do fixed-price, block-and-index and index energy contracts fix?
According to a 2005 Lawrence Berkeley National Laboratory study that interviewed eight competitive retail suppliers, a fixed price may cover energy, capacity, transmission and ancillary services in one charge or leave non-energy components to separate charges, and some fixed contracts add a volume band, with usage above it settled at a market index price. Ask each bidder which components its price covers and how usage outside the band settles.
Under block-and-index supply, in the Berkeley Lab study’s account, the buyer fixes the price of blocks of load and floats the rest, and usage below the block is, for example, credited at the spot price under symmetric terms or not at all under take-or-pay terms. According to a footnote in that study, capacity and ancillary services may stay hedged when energy follows the spot market. Ask which settlement rule applies before comparing block prices.
For natural gas, according to the National Petroleum Council’s December 2025 report to the Secretary of Energy, interruptible transport costs less than firm service but is more likely to be interrupted at peak demand. According to Brad Foster, an adviser whose firm sells energy procurement consulting, a fixed-basis, floating-NYMEX gas structure locks the regional differential and leaves commodity exposure open. Price hub, basis, transport and balancing separately for each site.
In a supplier’s sample agreement written for Pennsylvania service and filed with the District of Columbia Public Service Commission in July 2020, the price includes bypassable capacity, transmission, line-loss and ancillary charges but not the utility’s non-bypassable charges, and a regulatory-event clause lets the supplier pass through changes, such as higher transmission or capacity rates, that add $0.10 per MWh or more. Ask every bidder for its pass-through list and threshold, and have counsel read the clause.
How should a multi-site buyer normalize tariff data before sourcing?
Start with market status: according to the Department of Energy’s guide to electricity bills, a facility in a deregulated market can choose among providers, one in a regulated market buys only from its utility, and local public and cooperative utilities are often exempt from deregulation laws. Tag each account before choosing the sites for an event.
According to the same Department of Energy guide, demand charges, often listed as transmission and delivery charges, follow billed demand, which a ratchet clause can hold at a percentage of the previous 12 months’ maximum demand. Record each meter’s ratchet and twelve months of interval data: bidders price the load shape and the capacity and transmission tags, while billed demand and ratchets set the utility’s delivery charges, which no supplier changes. Give every bidder the same interval data and tags, and compare offers on total cost over that same load.
| Field | What to record | Source | Owner |
|---|---|---|---|
| Account | Utility, rate class, meters, contract end and notice dates | Bills, contracts | Procurement |
| Market status | Supplier choice or utility supply only | Tariff, state rules | Procurement, counsel |
| Load shape | Interval data, baseload, peaks, shutdowns | Utility or site meters | Site energy lead |
| Billed demand | Ratchet terms, demand-charge basis | Tariff, recent bills | Site energy lead |
| Peak tags | Capacity and transmission tags, and how each is set | Utility or supplier | Procurement |
| Gas delivery | Firm or interruptible transport, balancing and cash-out terms | Tariff, supplier confirmation | Procurement, plant |
| Contract terms | Fixed and passed-through parts, volume band, pass-through threshold, broker fee, credit support | Offer and contract | Procurement, treasury, counsel |
This guide’s method, not a tariff, legal or accounting test.
For price evidence, plant metering scope and event timing, see the manufacturing energy shock evidence map, the research on manufacturing electricity accounting boundaries and the demand aggregation guide.
How do capacity and transmission peak tags reach the bill?
In a May 2026 technical bulletin from the National Institutes of Health’s Office of Research Facilities, the PJM capacity charge follows a customer’s peak load contribution, its average demand in the five highest system-wide peak hours from June through September, rather than monthly consumption. Ask each utility how it sets every account’s tag, and each bidder which tag and clearing price it priced.
According to PJM’s report on its 2028/2029 base residual auction, published July 14, 2026, all prices cleared at the cap, and load hedged through self-supply or bilateral contracts is not exposed to clearing prices, a statement about load-serving entities’ wholesale hedges rather than a buyer’s supply contract. Ask whether a bid fixes capacity at a stated tag and price or passes the actual charge through.
According to the Department of Energy guide, a four coincident peak (4CP) charge averages a facility’s demand at the grid’s peak in the four highest-demand months, usually June through September, into the next calendar year’s demand. In the National Institutes of Health bulletin, a peak forecasting and load-reduction program cut one plant’s contribution by about 25% after the 2025/2026 price increase. Ask each supplier to state how a lower tag at any site changes its price.
How should a buyer stage purchases across tranches?
In a refereed 2014 study by Nicola Secomandi and Sunder Kekre, a numerical finding from their procurement model suggests that buying the demand forecast forward is nearly optimal on realistic natural gas instances, which supports buying forecast volumes forward rather than at spot. Staging those purchases in tranches is this guide’s method; how many steps, and what share of each period to fix, are risk-policy choices the study does not test.
According to EIA’s Short-Term Energy Outlook of November 10, 2026, the Henry Hub spot price averages $2.87 per MMBtu from November through March in its forecast, 16% below the previous month’s forecast, and severe cold could cause temporary price spikes. Write purchase triggers and tranche sizes into a treasury-owned risk policy, so a new forecast changes purchases only through that policy.
What should brokers and suppliers disclose?
In the sample agreement, a broker or consultant acts as the customer’s agent during the sale and may receive a commission that the supplier pays from the customer’s payments. According to the same adviser’s January 2026 article on broker pay, many brokers embed their compensation in the supply price, and margins can be added in later hedging transactions. Ask for every fee per MWh or MMBtu in writing, for each tranche.
Under the same sample agreement, the supplier may require credit support, such as a guaranty, letter of credit, deposit or prepayment, within five business days if it judges the customer’s credit unsatisfactory. Before awarding, ask each bidder and broker:
- Which bill components does the price fix, and which pass through at cost?
- Which tag values did the price assume, and how does a lower tag change it?
- How is usage outside the band, or below the block, settled?
- Which rule or rate changes pass through, and above what threshold?
- What broker or consultant fee is included per unit, now and in later tranches?
- What credit support can be demanded, and how fast must it be posted?
- For each delivery year, is capacity priced at a cleared auction result, an estimate, or trued up later?
- What usage change, site closure or on-site generation counts as a material change, and how is early termination priced?
Who should govern hedge decisions?
Give each decision an owner: procurement runs the event and site record, treasury owns the risk policy, limits and derivatives, the controller decides and documents the accounting, which the external auditor reviews, and counsel reviews clauses. According to EY’s October 2026 guide to derivatives and hedging, the normal purchases and normal sales exception requires probable physical delivery throughout the contract term, excludes contracts that settle gains or losses in cash periodically, and must be documented.
According to the same EY guide, ASU 2025-09 (November 2025) enhances or clarifies the guidance on hedging variable price components of nonfinancial forecasted transactions, effective for public business entities in fiscal years beginning after December 15, 2026, and a year later for others. Send designation and net settlement questions to treasury and the controller, who agrees the treatment with the auditor, before signing.
How will AI agents change enterprise energy procurement?
Frequently asked questions
What is a block-and-index energy contract?
According to the 2005 Berkeley Lab study, the buyer fixes the price of blocks of load and floats the rest at the market price, and the contract decides how usage below the block is credited.
What is a capacity tag?
In the National Institutes of Health bulletin on PJM charges, it is the customer’s peak load contribution, its average demand in the five highest system-wide peak hours from June through September, which sets the capacity charge.
Does a physical energy contract avoid derivative accounting?
Not by itself: according to EY’s October 2026 guide, the normal purchases and normal sales exception needs probable physical delivery throughout the term and a documented designation. Ask treasury and the controller whether each contract qualifies.
Sources
- 2028/2029 Base Residual Auction Report — PJM Interconnection, L.L.C., PJM Interconnection, July 14, 2026, 2026. Current empirical evidence (official report): The 2028/2029 auction (report of July 14, 2026) cleared all prices at the $325.00 cap per megawatt of unforced capacity per day; the cap and floor were also in effect for the 2026/2027 and 2027/2028 auctions (chart note); load hedged through self-supply or bilateral contracts is not exposed to auction clearing prices, which the guide describes as load-serving entities' wholesale hedges; Table 2 RTO clearing prices for 2022/2023 to 2028/2029 ($50.00, $34.13, $28.92, $269.92, $329.17, $333.44, $325.00), charted; a constrained zone can clear above the RTO price.
- Industrial Natural Gas Contracts: Why Price Alone Isn’t Enough — Brad Foster, Foster LLC (fosterec.com), February 19, 2026, 2026. Contextual evidence (practitioner article): The adviser's firm sells energy procurement consulting (site menu and contact panel); a fixed-basis, floating-NYMEX gas structure locks the regional differential and leaves commodity exposure open (attributed to the adviser).
- How Energy Brokers Get Paid: The Hidden Compensation Model Every Energy Buyer Must Understand — Brad Foster, Foster LLC (fosterec.com), January 20, 2026, 2026. Contextual evidence (practitioner article): Many brokers embed their compensation in the supply price rather than invoicing buyers, and further margins can be added in mid-contract hedging transactions (attributed to the adviser).
- Short-Term Energy Outlook: Natural gas (November 2026) — U.S. Energy Information Administration, U.S. Energy Information Administration, Short-Term Energy Outlook released November 10, 2026, 2026. Current empirical evidence (official report): EIA's outlook of November 10, 2026 forecasts the Henry Hub spot price to average $2.87 per MMBtu from November through March, 16% less than the previous month's forecast, and says severe cold in January and February could cause temporary price spikes.
- PJM Five Coincident Peaks (5CP) and Capacity Charges: A Data Science Approach (Technical Bulletin Issue 160) — Office of Research Facilities, National Institutes of Health, National Institutes of Health, Office of Research Facilities, Technical Bulletin Issue 160, May 2026, 2026. Current empirical evidence (official report): The PJM capacity charge is based on a customer's peak load contribution rather than monthly consumption; that contribution is the customer's average demand during the five highest system-wide peak hours from June through September; one central utility plant's peak forecasting and load-reduction program (forecasts flag likely peaks for operational review and possible load-shedding) cut its contribution by about 25% since the 2025/2026 price increase.
- Understanding Your Utility Bills: Electricity (ORNL/SPR-2021/1839) — Christopher Price, Alexandra Botts, Senthil Sundaramoorthy, Subodh Chaudhari and Thomas Wenning, Oak Ridge National Laboratory, U.S. Department of Energy, Better Buildings, Better Plants Program, 2021 (prepared by Oak Ridge National Laboratory); read through the Internet Archive capture of July 10, 2026, 2021. Foundational evidence (official report): A facility in a deregulated market can choose among several electricity providers, a facility in a regulated market can buy only from its utility, and local public and cooperative utilities are often exempt from state deregulation laws; demand charges, often listed on bills as transmission and delivery charges, follow billed demand; a ratchet clause sets a minimum billed demand from a percentage of the previous 12 months' maximum demand; some rate structures base demand charges on coincident peaks, and a 4CP charge averages demand at the grid's peak in the four highest-demand months, usually June through September, into the next calendar year's demand.
- Real Time Pricing as a Default or Optional Service for C&I Customers: A Comparative Analysis of Eight Case Studies (LBNL-57661) — G. Barbose, C. Goldman, R. Bharvirkar, N. Hopper and M. Ting (Lawrence Berkeley National Laboratory); B. Neenan (Neenan Associates), Lawrence Berkeley National Laboratory, August 2005 (report LBNL-57661 for the California Energy Commission PIER program; OSTI 891019), 2005. Foundational evidence (official report): All 8 suppliers interviewed offered fixed-price, spot-indexed and block-and-index supply; a fixed price may be one charge covering energy, capacity, transmission and ancillary services, or separate demand or customer charges may cover non-energy components; several suppliers add volume bands with usage above the band settled at a market index price; under block-and-index supply the buyer buys blocks at a fixed price and floats the rest, with usage below the block credited at the spot price (symmetric) or not credited (take-or-pay); capacity and ancillary services may stay hedged under spot-indexed supply.
- Optimal Energy Procurement in Spot and Forward Markets — Nicola Secomandi and Sunder Kekre (Tepper School of Business, Carnegie Mellon University), Manufacturing & Service Operations Management 16(2):270-282, INFORMS, Spring 2014; read through the Internet Archive capture of February 20, 2026, 2014. Foundational evidence (peer reviewed journal): A numerical finding of the authors' procurement model (keywords include newsvendor model) suggests that procuring the demand forecast in the forward market is nearly optimal on realistic natural gas instances; the guide uses it only as support for buying forecast volumes forward rather than at spot, and says that staging in tranches is the guide's method, not something the study tests.
- Financial reporting developments: Derivatives and hedging (revised October 2026) — Ernst & Young LLP, Ernst & Young LLP, Financial reporting developments, revised October 2026, 2026. Contextual evidence (practitioner article): The normal purchases and normal sales exception requires physical delivery to be probable at inception and throughout the contract term, cannot apply to a contract that settles gains or losses in cash periodically, and must be documented; ASU 2025-09 (November 2025) enhances or clarifies the guidance on hedging variable price components of nonfinancial forecasted transactions and applies to public business entities for fiscal years beginning after December 15, 2026, and to other entities a year later.
- Breakerbox, LLC supplier license applications (Formal Case Nos. EA 2020-04 and GA 2020-03): sample third-party supplier customer contract and bill — Breakerbox, LLC (filing letter); sample agreements and bills of third-party suppliers, Public Service Commission of the District of Columbia eDocket, filing of July 20, 2020, 2020. Contextual evidence (practitioner article): In the sample agreement, the price includes bypassable charges for capacity, transmission, line losses and ancillary services and excludes the utility's non-bypassable charges; the supplier may pass through cost changes such as higher network transmission or capacity rates that raise the price by $0.10 per MWh or more for the remaining term; any broker or consultant acts as the customer's agent and may receive a commission that the supplier pays from the customer's payments; the supplier may require credit support such as a guaranty, letter of credit, deposit or prepayment within five business days.
- Reliable Energy: Delivering on the Promise of Gas-Electric Coordination — National Petroleum Council, Committee on Gas-Electric Coordination, National Petroleum Council, report to the Secretary of Energy, December 3, 2025 (energy.gov), 2025. Contextual evidence (official report): FERC required pipelines to separate sales from transportation; interruptible transportation offers flexibility and lower cost than firm service but carries a higher risk of interruption during peak demand; cash-outs settle gas imbalances, usually monthly; pipelines must let shippers offset and trade imbalances.